After more than two decades and attempts of four administrations to implement, as of June 2016, the 147-km., 35 stations NSCR Project, had zero awarded contracts, zero physical progress, and zero trains ordered / started production.
Worse, the latest attempt to implement the project ended up in a protracted legal battle in international arbitration (Northrail vs. SINOMACH), which threatened to further delay and stall progress on the NSCR Project as of June 2016.
Loading...
On going construction of NSCR |
Now, with assistance from the Japanese Government / Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB), PNR Clark Phase 1 (Tutuban-Malolos; 38 km.) and PNR Clark Phase 2 (Malolos-Clark; 53 km.) are now in full swing construction, and delivery of the NSCR’s 58 8-car Train Sets (464 Train Cars or bagons) have started, with the 1st Train Set already delivered in November 2021. Meanwhile, all nine civil works contracts for the construction of PNR Calamba (Manila-Calamba; 56 km.) are about to be awarded within the 1st quarter of 2022.
As of December 2021, PNR Clark 1 has a 53.85% overall progress rate, PNR Clark 2 has a 34.46% overall progress rate, and PNR Calamba has a 28.62% overall progress rate.
Did you know that different segments of the North-South Commuter Railway (NSCR) Project were attempted to be implemented: 1st in 1994 together with the government of Spain and the private sector (a.k.a. Northrail Project); 2nd in 1999 together with the government of Japan (JBIC); 3rd in 2004 together with the government of South Korea (a.k.a. North-South Linkage Project); and 4th from 2002-2011 together with the government of China (a.k.a. Northrail Project)?
After more than two decades and attempts of four administrations to implement, as of June 2016, the 147-km., 35 stations NSCR Project, had zero awarded contracts, zero physical progress, and zero trains ordered / started production.
Worse, the latest attempt to implement the project ended up in a protracted legal battle in international arbitration (Northrail vs. SINOMACH), which threatened to further delay and stall progress on the NSCR Project as of June 2016.
In 2017, I, as Northrail ex-officio Chairman, and BCDA President Vince Dizon, concluded a historic out-of-court Settlement Agreement of the legal dispute with SINOMACH, which saved the Philippine government more than PHP5 billion ($100 million) in potential payment of claims to SINOMACH, and hundreds of millions more in legal fees and arbitration costs.
Now, with assistance from the Japanese Government / Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB), PNR Clark Phase 1 (Tutuban-Malolos; 38 km.) and PNR Clark Phase 2 (Malolos-Clark; 53 km.) are now in full swing construction, and delivery of the NSCR’s 58 8-car Train Sets (464 Train Cars or bagons) have started, with the 1st Train Set already delivered in November 2021.
After more than two decades and attempts of four administrations to implement, as of June 2016, the 147-km., 35 stations NSCR Project, had zero awarded contracts, zero physical progress, and zero trains ordered / started production.
Worse, the latest attempt to implement the project ended up in a protracted legal battle in international arbitration (Northrail vs. SINOMACH), which threatened to further delay and stall progress on the NSCR Project as of June 2016.
In 2017, I, as Northrail ex-officio Chairman, and BCDA President Vince Dizon, concluded a historic out-of-court Settlement Agreement of the legal dispute with SINOMACH, which saved the Philippine government more than PHP5 billion ($100 million) in potential payment of claims to SINOMACH, and hundreds of millions more in legal fees and arbitration costs.
More importantly, the Settlement Agreement removed this legal obstacle to the progress of the NSCR Project.
Now, with assistance from the Japanese Government / Japan International Cooperation Agency (JICA) and the Asian Development Bank (ADB), PNR Clark Phase 1 (Tutuban-Malolos; 38 km.) and PNR Clark Phase 2 (Malolos-Clark; 53 km.) are now in full swing construction, and delivery of the NSCR’s 58 8-car Train Sets (464 Train Cars or bagons) have started, with the 1st Train Set already delivered in November 2021.
RELATED: Construction of 380-km Laguna-Albay PNR route to start soon
Meanwhile, all nine civil works contracts for the construction of PNR Calamba (Manila-Calamba; 56 km.) are about to be awarded within the 1st quarter of 2022.
As of December 2021, PNR Clark 1 has a 53.85% overall progress rate, PNR Clark 2 has a 34.46% overall progress rate, and PNR Calamba has a 28.62% overall progress rate.
The NSCR System will cut travel time from Clark International Airport to Calamba, Laguna from over 4 hours to as short as 1 hour and 30 minutes, and is expected to serve more than 1 million passengers per day after full operations.
Construction of NSCR South commenced on July 3, 2023, following the cessation of the Calamba–Alabang commuter services the previous day.
In March 2024, the Philippine National Railways (PNR) announced the suspension of operations of Governor Pascual–Tutuban and Tutuban-Alabang routes to make way for the construction of the North-South Commuter Railway (NSCR) project.
via DOTr
OTHER TRANSPORTATION INFO IN PH
- List of Bus Terminals in the Philippines
- Metro Manila Bus Transit Map
- List of Ferry Operators in the Philippines
- List of Airlines in the Philippines
- List of Airports in the Philippines
- List of Railways and Metro Rail Lines in the Philippines
- List of Major Roads in Metro Manila
- List of Expressways and Tollways in the Philippines
north-south commuter railway update north-south commuter railway project map north-south commuter railway project contractor north-south commuter railway phase 1 south commuter railway project philippines north rail project cancelled north-south railway project philippines north-south commuter railway extension project
No comments
Let us know your thoughts!